In 2024, 118,700 m2 of total floor area of public sector buildings were renovated within the cohesion policy programs, and in the period 2021–2024, 548,200 m2 or 60% of the value planned in the Long-term strategy for energy renovation of buildings by 2050. Within the OP EKP 1.08 million m2 of total floor area were renovated by the end of 2024, which is at the level of the OP EKP target value. For the energy renovation of buildings owned and occupied by the central government the gap behind the target from OP EKP was significant. Under the obligation from Article 5 of the EED from 2012, 91,146 m2 of floor area were renovated by the end of 2024 or only 31% of the 2014–2024 target. In the period 2014-2024, the annual renovation target was achieved only in 2018, while the cumulative target was never achieved.
Jožef Stefan Institute - Energy Efficiency Centre
| Cumulative floor area of energy renovated buildings[1.000 m2] | Expected value in 2025[1.000 m2] | Annual indicative values up to 2020[1.000 m2] | |
|---|---|---|---|
| 2011 | 0 | ||
| 2012 | 58.83 | 63.27 | |
| 2013 | 513.29 | 301.04 | |
| 2014 | 952.67 | 538.82 | |
| 2015 | 1241.73 | 776.59 | |
| 2016 | 1241.73 | 980.28 | |
| 2017 | 1243.83 | 1183.97 | |
| 2018 | 1488.40 | 1387.66 | |
| 2019 | 1676.65 | 1591.35 | |
| 2020 | 1803.72 | 1795.04 | |
| 2021 | 1917.57 | ||
| 2022 | 2083.14 | ||
| 2023 | 2233.23 | ||
| 2024 | 2351.90 | 2351.90 | |
| 2025 | 2380.74 | ||
| 2026 | |||
| 2027 | |||
| 2028 | |||
| 2029 | |||
| 2030 |
Jožef Stefan Institute - Energy Efficiency Centre
| Cumulative floor area of energy renovated buildings [1.000 m2] | Expected value in 2025 [1.000 m2] | Annual indicative values up to 2030 [1.000 m2] | |
|---|---|---|---|
| 2021 | 113.86 | 230 | |
| 2022 | 279.43 | 460 | |
| 2023 | 429.51 | 690 | |
| 2024 | 548.18 | 548.18 | 920 |
| 2025 | 577.02 | 1150 | |
| 2026 | 1380 | ||
| 2027 | 1610 | ||
| 2028 | 1840 | ||
| 2029 | 2070 | ||
| 2030 | 2300 |