KAZALCI OKOLJA

Key message
Good

At the end of 2018, the total floor area of energy-renovated buildings in the public sector amounted to 1.51 million m2, which exceeds the indicative annual target by 9%. In 2018, more than 250,000 m2 were renovated, which is significantly more than in 2017, but still lags behind the values of annually renovated floor area in the period 2013−2015. In order to achieve the 2020 target, a floor area of just under 140,000 m2 will need to be renovated annually in the period 2019−2020. Together with this indicator, it is also necessary to consider the results of indicators for monitoring the CO2 emissions reduction and final energy savings achieved through the implementation of measures in the public sector.


Charts

Figure PO08-1: Cumulative floor area of energy-renovated buildings in the public sector in the period 2011−2018, expected values of the indicator in 2019 and 2020 and its target values up to 2020
Show data
Target values of the indicator Expected value of the indicator in 2019 and 2020 Indicator values in the period 2011−2018
2011 0
2012 63.27 63.27
2013 301.04 522.62
2014 538.82 972.66
2015 776.59 1261.72
2016 980.28 1261.72
2017 1183.97 1265.05
2018 1387.66 1515.15 1515.15
2019 1591.35 1661.30
2020 1795.04 1986.01

Methodology

The indicator methodology is available only in Slovene (link to the indicator)

Date of data source summarization